Project Updates

Blasting Updates

Next Blast:
Cut 6 – M11 Tuesday 10/10/2017  Time: 3.00pm

 

 * Locations, dates and times are subject to change. Please check daily for updates.

 

What is happening now?

 

Major progress has been achieved over the last three months at the New M11 Gorey to Enniscorthy motorway project. The weather improvement in these months has been advantageous and our teams Bam Civil and Dragados in joint venture (M11 EJV),  have been prepared for this. New work fronts have opened up for Structures & Earthworks teams and the progress is visible throughout our site.

BAM & Iridium are conscious of ensuring that both the local community and the wider region have opportunities to benefit from the construction as well as future operations and maintenance activities during this project and welcome all interested parties to contact us, and apply directly or through our subcontractors.

A lot of progress has been achieved during the last three months on our project.

  • Earthworks continue and new work fronts have been opened up during the last three months.
  • 5 Roads have already been diverted through alternative routes at Rockspring, Knockrathkyle and Scurlocksbush, Monart, and Killaligan in order to allow the construction of new bridges over the future motorway. All of them are due to be reopened by early September and more Roads will be diverted with a target to have most of the Structure works completed by the first quarter of 2018.
  • Interceptor drainage, silt fencing and siltation ponds/settlement lagoons have been installed along the scheme to mitigate the effect of the works on the surface water network.
  • Drainage works for the carriageway have commenced and we are preparing ourselves in order to be ready to commence Pavement works in the next few months.

 

Main Structures Update

15 Bridges are currently under progress and our structures team is increasing its resources in order to coordinate the works and meet our deadlines.

 

 

 

 

Below is a summary of expected works over the coming months:

Q3 2017
  • Minor Outstanding Detailed Design
  • Well Monitoring/ Noise and Vibration Monitoring
  • Pre-earthworks drainage
  • Earthworks
  • Drainage
  • Structures (Culverts)
  • Structures (Access Structures)
  • Structures (Bridges)
  • Side Road Works
  • Initial Pavement Works

 

Q4 2017
  • Well Monitoring/Noise and Vibration Monitoring
  • Earthworks
  • Drainage
  • Structures (Bridges)
  • Side Road Works
  • Pavement Works

 

Our Newsletters

M11 Gorey to Enniscorthy PPP Scheme Newsletter – Issue 7

M11 Gorey to Enniscorthy PPP Scheme Newsletter Issue 6

M11 Gorey to Enniscorthy PPP Scheme Newsletter Issue 5

M11 Gorey to Enniscorthy PPP Scheme Newsletter Issue 4

M11 Gorey to Enniscorthy PPP Scheme Newsletter – Issue 3

M11 Gorey to Enniscorthy PPP Scheme Newsletter – Issue 2

M11 Gorey to Enniscorthy PPP Scheme Newsletter – Issue 1

Scéim CPP an M11 ó Ghuaire go hInis Córthaidh – Eisiúint 1