Project Updates

Blasting Updates

Next Blast:
Cut 4- N30 Friday 30/06/2017   Time: 3.00pm

 

 * Locations, dates and times are subject to change. Please check daily for updates.

 

What is happening now?

Site Clearance Works are nearing completion in the area from Scarawalsh Roundabout up to the River Slaney which is going to form the new N80 road connecting the mainline of the M11 to the new N30 where works have advanced further. Earthworks continue at the areas adjacent to Clogh,  Rockspring,  Knockrathkyle, Ballyorril and Templescoby. Excavation of rock by means of blasting at the locations of Clogh, Knockrathkyle and also next to the River Urrin are ongoing and each blast is closely controlled and monitored. Three roads have already been closed at Rockspring, Monart, and Killaligan, in order to construct new bridges and more road diversions are due to be in place in the next months. Interceptor drainage, silt fencing and siltation ponds/settlement lagoons have been installed along the scheme to mitigate the effect of the works on the surface water network. The works for Access Structures are also progressing well and we intend to maintain access for the local landowners in the areas where works are ongoing.

 

Main Structures Update

There are also 10 Bridges in total where works are in progress currently at the areas adjacent to Rockspring, Knockrathkyle , Killaligan and Monart.

Works have commenced for the Bridge over the Railway line near Clogh, where the North abutment is already in place and ground improvement works are ongoing at the Abutment South of the railway line. The Beams are also being fabricated and will be placed in the next 3 months.

Piling works have also started for the Bridge that will cross over the Slaney River and the existing Railway line. The Construction of the abutments and Pier will start in the next months and the works will continue until the first quarter of 2018 at this location.

There are also works ongoing at the Area of River Urrin for the Bridge that is going to cross over the river and the existing road at that location. Currently the piling for the foundation of the structures are being casted and testing is ongoing in order to continue with the Abutment works.

 

 

 

 

 

 

 

 

 

 

 

 

Below is a summary of expected works over the coming months:

Q2 2017
  • Minor Outstanding Detailed Design
  • Well Monitoring/ Noise and Vibration Monitoring
  • Pre-earthworks drainage
  • Earthworks
  • Drainage
  • Structures (Culverts)
  • Structures (Access Structures)
  • Structures (Bridges)
  • Side Road Works

 

Q3 2017
  • Minor Outstanding Detailed Design
  • Well Monitoring/ Noise and Vibration Monitoring
  • Pre-earthworks drainage
  • Earthworks
  • Drainage
  • Structures (Culverts)
  • Structures (Access Structures)
  • Structures (Bridges)
  • Side Road Works
  • Initial Pavement Works

 

Our Newsletters

M11 Gorey to Enniscorthy PPP Scheme Newsletter Issue 6

M11 Gorey to Enniscorthy PPP Scheme Newsletter Issue 5

M11 Gorey to Enniscorthy PPP Scheme Newsletter Issue 4

M11 Gorey to Enniscorthy PPP Scheme Newsletter – Issue 3

M11 Gorey to Enniscorthy PPP Scheme Newsletter – Issue 2

M11 Gorey to Enniscorthy PPP Scheme Newsletter – Issue 1

Scéim CPP an M11 ó Ghuaire go hInis Córthaidh – Eisiúint 1