Project Updates

Blasting Updates

Next Blast:

 

Cut 4 – N30 – Tuesday 21/03/2017 at 2.00pm

 

What is happening now?

The Works for the M11 Gorey to Enniscorthy Project ramp up as we are entering 2017. Earthworks are ongoing at the areas adjacent to Clogh,  Rockspring,  Knockrathkyle and Ballyorril. Blasting of rock at the locations of Clogh and Knockrathkyle has also started since last December and each blast is closely monitored.  New road diversions are due to be in place in order to accommodate the construction of local roads and the building of new bridges. Interceptor drainage, silt fencing and siltation ponds/settlement lagoons have been installed along the scheme to minimise the effect of the works on the  surface water network. Works are also due to commence for the new bridges over the Railway Line near Clogh, over the Slaney River and at The Urrin River as well as at Rockspring, Knockrathkyle , Killaligan and Monart.

 

 

Below is a summary of expected works over the coming months:

Q1 2017
  • Continuation of Detailed Design
  • Well monitoring/Noise and Vibration Monitoring
  • Pre-earthworks drainage
  • Top soil strip
  • Earthworks
  • Structures (Culverts)
  • Structures (Access Structures)
  • Structures (Bridges)
  • Side Roads Works

 

Q2 2017
  • Minor Outstanding Detailed Design
  • Well Monitoring/ Noise and Vibration Monitoring
  • Pre-earthworks drainage
  • Earthworks
  • Drainage
  • Structures (Culverts)
  • Structures (Access Structures)
  • Structures (Bridges)
  • Side Road Works

 

Our Newsletters

M11 Gorey to Enniscorthy PPP Scheme Newsletter Issue 5

M11 Gorey to Enniscorthy PPP Scheme Newsletter Issue 4

M11 Gorey to Enniscorthy PPP Scheme Newsletter – Issue 3

M11 Gorey to Enniscorthy PPP Scheme Newsletter – Issue 2

M11 Gorey to Enniscorthy PPP Scheme Newsletter – Issue 1

Scéim CPP an M11 ó Ghuaire go hInis Córthaidh – Eisiúint 1